41-U.S.C.-3309

41-U.S.C.-3309

§3309 – Design-Build Selection Procedures

Pathway

Title 41 > Subtitle I > Division C > Chapter 33 > Section 3309

Details

  • Reference: Section 3309
  • Legend: §3309 – Design-Build Selection Procedures
  • USCode Year: 2013

Provision Content

(a) Authorization.—Unless the traditional acquisition approach of design-bid-build established under sections 1101 to 1104 of title 40 or another acquisition procedure authorized by law is used, the head of an executive agency shall use the two-phase selection procedures authorized in this section for entering into a contract for the design and construction of a public building, facility, or work when a determination is made under subsection (b) that the procedures are appropriate for use.

(b) Criteria for Use.—A contracting officer shall make a determination whether two-phase selection procedures are appropriate for use for entering into a contract for the design and construction of a public building, facility, or work when—

(1) the contracting officer anticipates that 3 or more offers will be received for the contract;

(2) design work must be performed before an offeror can develop a price or cost proposal for the contract;

(3) the offeror will incur a substantial amount of expense in preparing the offer; and

(4) the contracting officer has considered information such as the following:

(A) The extent to which the project requirements have been adequately defined.

(B) The time constraints for delivery of the project.

(C) The capability and experience of potential contractors.

(D) The suitability of the project for use of the two-phase selection procedures.

(E) The capability of the agency to manage the two-phase selection process.

(F) Other criteria established by the agency.

(c) Procedures Described.—Two-phase selection procedures consist of the following:

(1) Development of scope of work statement.—The agency develops, either in-house or by contract, a scope of work statement for inclusion in the solicitation that defines the project and provides prospective offerors with sufficient information regarding the Federal Governments requirements (which may include criteria and preliminary design, budget parameters, and schedule or delivery requirements) to enable the offerors to submit proposals that meet the Federal Governments needs. If the agency contracts for development of the scope of work statement, the agency shall contract for architectural and engineering services as defined by and in accordance with sections 1101 to 1104 of title 40.

(2) Solicitation of phase-one proposals.—The contracting officer solicits phase-one proposals that—

(A) include information on the offerors—

(i) technical approach; and

(ii) technical qualifications; and

(B) do not include—

(i) detailed design information; or

(ii) cost or price information.

(3) Evaluation factors.—The evaluation factors to be used in evaluating phase-one proposals are stated in the solicitation and include specialized experience and technical competence, capability to perform, past performance of the offerors team (including the architect-engineer and construction members of the team), and other appropriate factors, except that cost-related or price-related evaluation factors are not permitted. Each solicitation establishes the relative importance assigned to the evaluation factors and subfactors that must be considered in the evaluation of phase-one proposals. The agency evaluates phase-one proposals on the basis of the phase-one evaluation factors set forth in the solicitation.

(4) Selection by contracting officer.—

(A) Number of offerors selected and what is to be evaluated.—The contracting officer selects as the most highly qualified the number of offerors specified in the solicitation to provide the property or services under the contract and requests the selected offerors to submit phase-two competitive proposals that include technical proposals and cost or price information. Each solicitation establishes with respect to phase two—

(i) the technical submission for the proposal, including design concepts or proposed solutions to requirements addressed within the scope of work, or both; and

(ii) the evaluation factors and subfactors, including cost or price, that must be considered in the evaluations of proposals in accordance with subsections (b) to (d) of section 3306 of this title.

(B) Separate evaluations.—The contracting officer separately evaluates the submissions described in clauses (i) and (ii) of subparagraph (A).

(5) Awarding of contract.—The agency awards the contract in accordance with chapter 37 of this title.

(d) Solicitation To State Number of Offerors To Be Selected for Phase-Two Requests for Competitive Proposals.—A solicitation issued pursuant to the procedures described in subsection (c) shall state the maximum number of offerors that are to be selected to submit competitive proposals pursuant to subsection (c)(4). The maximum number specified in the solicitation shall not exceed 5 unless the agency determines with respect to an individual solicitation that a specified number greater than 5 is in the Federal Governments interest and is consistent with the purposes and objectives of the two-phase selection process.

(e) Requirement for Guidance and Regulations.—The Federal Acquisition Regulation shall include guidance—

(1) regarding the factors that may be considered in determining whether the two-phase contracting procedures authorized by subsection (a) are appropriate for use in individual contracting situations;

(2) regarding the factors that may be used in selecting contractors; and

(3) providing for a uniform approach to be used Government-wide.

(Pub. L. 111–350, §3, Jan. 4, 2011, 124 Stat. 3759.)

Historical and Revision Notes
Revised
Section
Source (U.S. Code) Source (Statutes at Large)
3309 41:253m. June 30, 1949, ch. 288, title III, §303M, as added Pub. L. 104–106, div. D, title XLI, §4105(b)(1), Feb. 10, 1996, 110 Stat. 647.

In subsections (a) and (c)(1), the words sections 1101 to 1104 of title 40 are substituted for the Brooks Architect-Engineers Act (title IX of this Act) and the Brooks Architect-Engineers Act (40 U.S.C. 541 et seq.), respectively, because of section 5(c) of Public Law 107–217 (40 U.S.C. note prec. 101) and for consistency with title 40.

In subsection (c)(5), the reference to section 253b of this title is limited to chapter 37 of the revised title for clarity.

U.S. Encyclopedia of Law Coverage

41-U.S.C.-3309 in the Legal Encyclopedia: Public Contracts

In this entry about 41-U.S.C.-3309, find legal reference material, bibliographies and premiere content related to public contracts in the American Encyclopedia of Law, presenting a comprehensive view of the United States public contracts-specific issues, written by authorities in the field.

41-U.S.C.-2310 in the Legal Encyclopedia: Procurement

In this entry about 41-U.S.C.-2310, find legal reference material, bibliographies and premiere content related to procurement in the American Encyclopedia of Law, presenting a comprehensive view of the United States procurement-specific issues, written by authorities in the field.

41-U.S.C.-3307 in the Legal Encyclopedia: Federal Procurement Policy

In this entry about 41-U.S.C.-3307, find legal reference material, bibliographies and premiere content related to federal procurement policy in the American Encyclopedia of Law, presenting a comprehensive view of the United States federal procurement policy-specific issues, written by authorities in the field.

Topic Map


Posted

in

,

by

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *